C4 has the will to resolve C3 C3 detail inspections ladder from the completion of the construction was completed as previously promised. Since it can not be used
as there is coordination between C3 and C4 have mutually agreed to detail inspections ladder to fix a new, detailed in Attachment no.1
C3 Additional information that will accelerate the preparation of shop drawing. detail inspections ladder revised to be completed soon, and sent for approval to the PCPL.