Having checked the measurement against the BOQ items & IFC drawings details, and found minor things to complete as follows;
· The summary page is now updated as per attached (some heading in measurement sheets have been updated).
· Purpose is to put the quantities of works to the right items of the BOQ, and the new items are to add as necessary.
· Grating is to keep in m2 and put in the BOQ item as provided for it, measurement in tonnes is not acceptable, and this will reduce a lot of money.
· The ladders 1-4 are found as “shipped loose item” and to be measured separate following standard details in tonnes.
· The stairs ST-1 are to measure in separate item as per standard details.
· The summary_B6PA is to revise following the summary page.
Please review and give me a call for further discussion and completion on this.