To calculate revenue recognition, construction cost. The construction costs and profit from the construction of annual. 2545
rate stage success of construction contract =] ((225 × 100) / 1 500), 15%
= revenue recognition for construction of the year 2545. =], (2 000 × 15) / 100)
.= 300 million
perception construction costs of 2545 = 225 million
perception due to the construction of 2545 = 300 - 225
= 75 million
.