Prosecute those who say prosecute mercenary contracts, construction, Samut prakan, Samut sakhon-cable dirt road to defendant 1 by period of construction, completed within a day, but because of the 420 defendant could not deliver people to prosecute area have included 97 days period after receiving the construction area and then prosecute those about barriers, flood area vs. construction makes the PMO cannot perform the construction to be completed as specified in the contract. Those lawsuits have books down such barriers 2545 Notice October 14, and extend my contract and have the book down to November 5, the Committee Chairman, 2545 hired to extend my contract. 2 the defendant has resolved not to extend the construction period claiming that flood conditions up and down naturally from time to time, which may have a very high water level, but not flooding area buildings. Those books are, therefore, to prosecute the Governor Dru disputed the results of the appeal are determined not to extend the contract period. Subsequently, the defendant who has 1 notice that prosecute floods of such construction areas caused by the natural tide conditions. Conclusive force majeure to consider extending the duration of the contract in accordance with regulation 139 (2) of the Prime Minister's Office regarding the parcel cannot be extended-2535 (1992) construction who prosecute found no extends Diagnostics contract construction is the use of discretion by. Unfair to people and prosecute administrative command is to prosecute corrupt must be adjusted in accordance with the contract. Ask them to revoke command do not extend the period of the construction contract and the defendant, both songonumat, expand, contract, construction period such acts possible. The Court ruled the complaint consider the initial check and see whether or not to approve the construction of the extension period, the contract is exercised in accordance with the agreement. Not to use administrative powers. The command of the defendant did not approve the buyout, 1 construction, the contract thus dwelling by command, and the case is a dispute about administrative contract. Part request asking the Court's order, the defendant, songonumat both extend the contract managers to prosecute it. The administrative court may not just have the force of such extension period. So does prosecute people have the right to prosecute under section 42, paragraph one of section 112 of the establishment of the Court so pokkhrong command is rejected and placed out of the lawsuit, meaning the Canon. Diagnosed by the Supreme Administrative Court that the said contract of the 21 in the case determined that force majeure or any cause why the contractor is unable to complete the work according to the defined time of dwelling contractors. The contractors will be required to provide such notice to the employer's request, extend the time in which to extend the deadline, construction contract is in the discretion of the employer are considered as deemed appropriate. The Administrative Court does not have the power to define a force either party to act or refrain from wenkratham, one of the other than, or different from, that the parties have agreed in the contract. It is a request that the Court could not determine the force in accordance with article 72, paragraph one has (3) of section 112 of the establishment of the Court, therefore, does not prosecute people pokkhrong have the right to sue the defendant in accordance with article 42 paragraph 1 1. The Act such that the appeal made prosecute 139 hotels on the Prime Minister's Office parcel regulations 2535 (1992) is just not only practices the powers of the parties agree that these terms appear in the text of the contract dispute in 21.This lawsuit, it is at the discretion of the defendant by the Governor as an employer in the Samut prakan province to consider the buyout contract by construction and prosecute the defendant 1. To prosecute those that appeal to allow or not allow to extend the contract period of construction is to use the power of its cherished acts both, but only one faction. The command did not approve, extend the period of the contract is therefore the construction of administrative commands. Cases, so there is a dispute occurs, then it is entitled to use cases defined in the contract as a contract of employment as an Office for the use of that legal powers of the authorities that prosecute people's rights, thus affected not by command, according to section 5 Hotels.Government administrative practices of accountability for 2539 (1996) command of the defendant did not approve the buyout, (ii) the construction of the contract, then the dwelling, (ii) the defendant, or as head of the Government employer in accordance with the agreement. Therefore, there is no authority to approve or not approve the order to extend the contract period of construction. The cause of this is due to the lawsuits that the defendant did not approve, extend the period of the construction contract. Those lawsuits are not entitled to sue the defendant in accordance with article 42, paragraph 2 of section 112 of the establishment of the Court, the administrative court pokkhrong initial command is rejected and into account. It stands out by order of the initial administrative court.
การแปล กรุณารอสักครู่..