One batch shall be sampled at random from every 30 m3 of concrete placed, and not
less than one sample shall be taken for each class of concrete placed each day. For
strength tests three independent test cylinders, taken from each batch to be sampled,
shall be made; one cylinder shall be tested at 7 days and the other two at 28 days, or as
directed by the Employer's Representative.