The results can offer the ways to improve the working process by reducing the cycle time. Using technology to improve all 3 precast process is graded filter can be reduced from 14 days left 3 days I 1 beam process decreased from 30 days. Left 21 days and process column decreased from 6 days left 3 days, which can reduce the cycle time of 151 days reduced to 127 days were 15.89 and also the analysis of cost, improve cost all, all, 1 362 247.50 baht. After the improvement, reduced to 1 233 465.06, value, were 9.45 concluded that the process of construction, the technology to make the better performance. As a result, the working period and low cost, lower down the reasons of profit that increase. It also can meet the needs of customers quickly.