The title, reducing the time in the process of corrugated paper box
case study company, S. P. wallpaper.
Ltd abstract the purpose of this research is to reduce the time in the process of corrugated paper box case study company, S. P.Paper Co., Ltd. from the study of the process by using the principle of work and basic study of time, that the procedure are all 19 steps. The time in the process of corrugated paper box of 900 sheet, is 30889 seconds or 8 hours 58 minutes, which the company must pay working overtime work in the research of the principles of ECRS used as a guideline to improve the production process of corrugated paper box.8 hours 58 minutes, only 7 hours 37 minutes or reduce the time to 1 hours 21 minutes thinking for lower 14.03% and streamline production process from the 19 steps left 16 steps. Which can reduce the working overtime down
key words: reducing the time / manufacturing process of corrugated paper box
.