TOC will be required to provide a presentation and, as follows:
With reference to the below email, the pending items relate to the training floors; we understand that it is the intention to go ahead with additional clients training floors.
To date, MTL have not undertaken any study on the effects to MEP plant, nor have we received architectural layouts etc.Should MTL submit a proposal for additional works (please see attached email)?