4.1 Introduction
Five tests were performed for this Study using the instrumented Retaining Wall facility.
The Test procedures, Materials, and results for the instrumented Retaining Wall tests are Presented
in the following Sections.
4.2 Test Procedures and Materials
This section describes the Test procedures and Materials. used in the instrumented
tests Retaining Wall. The backfill Material, Compaction Equipment, Wall Preparation activities,
backfill placement and Compaction procedures, cyclic Testing procedures, and the instrumented
Retaining Wall Test Schedule are described.
4.2.1 Backfill
The backfill used for the instrumented tests Retaining Wall Sand Castle Light is obtained
from. a quarry in Craig County, Virginia. Light Sand Castle is a Clean, Fine Sand consisting
predominantly of subangular Quartz grains. FILZ and Duncan (in 1992) performed Various
Laboratory tests on Light Sand Castle. Sand for this, it was that 68 percent of the Material Found
passes the Sieve No. 40 and less than 1 percent passes the No. 200 Sieve. The coefficient of
uniformity and coefficient of curvature were determined to be 1.8 and 0.9, respectively.
Therefore, the Sand classifies as a poorly Graded Sand (SP) according to the Unified Soil
Classification System. The specific gravity of solids is 2.65. Minimum and maximum the
ASTM D4253-83 and ASTM D4254-83 densities are determined by 106 and 88.5 pounds per
Cubic Foot, respectively.
FILZ and Duncan (one thousand nine hundred ninety-two) Two performed tests using instrumented Retaining Wall Light
Sand Castle, but Without a compressible inclusion. The average weight of the compacted UNIT
17
Sand was approximately 105.5 PCF, corresponding to a density of nearly 100 Relative percent.
The estimated Friction Angle of the compacted Sand was 42 Degrees.
4.2.2 Compaction Equipment
For this Study, Two Hand-operated Compactors. were used: a Wacker Model BS60Y
(Rammer Compactor) and a Model Wacker BPU 2240A (Vibrating Plate Compactor). Schematic
diagrams are shown in Figure 4.1 of both Compactors. Powered by the Rammer Compactor is a 4
horsepower, 2-Cycle Engine that Drives a ramming Steel Shoe Into Contact with the soil at a
rate of 10 blows per Second percussion. The operating weight of the Rammer Compactor is 137
pounds. Vibrating Plate Compactor is the Powered by a 5 horsepower, 4-Cycle Engine that Drives
Eccentric Rotating counter-Weights. Rotate these Weights at a frequency of 100 Hz and About are
Connected by a Steel Plate that Contacts axles to the soil. The operating weight of the Vibrating
Plate Compactor is 275 pounds.
The Vibrating Plate Compactor Rammer and used for this Study are commonly employed
for Compaction in confined areas and adjacent to Retaining Wall Structures.
These Compactors are different in their mode of Operation. In a Study by FILZ and Duncan (the 1,992th)
Research on the Two Compactors used for this, it was delivered Compactor Rammer Found that the
higher Peak Contact Forces to the soil than the Vibrating Plate Compactor. Thus, higher
Compaction Earth-induced pressures Can be expected in compacted backfill with the Rammer
Compactor than in compacted backfill with the Vibrating Plate Compactor.
4.2.3 Wall Preparation Prior to Compaction
Wall Preparation consisted of lubricating the End and Far Walls of the backfill Area. and
placing on the instrumented TerraFlex Wall. Lubrication of the End and Far Walls was
18
a) Rammer Compactor
Figure 4.1: Schematic diagrams of a) Rammer Compactor and B) Vibratory Plate
Compactor (After FILZ and Duncan 1992)
Eccentric
Weights
Base
Plate
Shock
Absorber
B) Vibrating Plate Compactor
19
performed in. Order to minimize the buildup of shear stresses along these Walls, which could
influence the Test results. Allows the lubrication facility to more closely a 2-D Model Case of an
infinitely long and infinitely Wall Wide Area backfill (one thousand nine hundred ninety-two FILZ and Duncan). To lubricate the
End and Far Walls, a 6-MIL Sheet of polyethylene was taped in Place these on Walls. A thin layer
of grease Bearing wheel was Applied to the polyethylene Sheet, which was then covered with a
polyethylene Second Sheet. Walls were lubricated for all the tests performed Five.
The TerraFlex was delivered in pre-Cut Blocks of the desired thickness. The TerraFlex
was then Placed on the Face of the instrumented Retaining Wall GEOTECH using DB-784 adhesive
supplied by GEOTECH Systems Corporation. Applied over the TerraFlex was the full height and
Extended Length of the instrumented Wall and 2.5 feet from the instrumented panels onto the Wall
in the Area Access ramp.
4.2.4 Backfill Placement and Compaction
Before it was used as backfill in the instrumented Retaining Wall Test. facility, the Light
Sand Castle was less than 0.1 percent to hydroscopic Dried Moisture and stockpile Placed in a Dry
Area. The Sand was moved from the stockpile to the backfill Area Area by a Hopper lifted by an
overhead Crane. After depositing the Sand backfill in the Area, it was spread by Hand in Loose lifts
of sufficient thickness to Produce a compacted lift thickness of 6 inches. Placed Backfill was
approximately 6.5 feet against the High Wall instrumented for each Test.
The Rammer Compactor Peak delivers higher Forces to the soil than the Vibrating Plate
Compactor. For tests using the Rammer Compactor, each lift was compacted backfill with 2
passes. Vibrating Plate Compactor for the tests using, 5 passes were used to Compact each lift.
Both procedures produced Relative densities near 100 percent.
การแปล กรุณารอสักครู่..
