The connection system of the MEA
companies need to coordinate with meaTo get the parameters of welding spot on the parameters? To apply in the design of the generator. In order to prevent the loss of or short circuit, which mea specified must not exceed 25%
.The fact TTCL not synchronize with mea but was designed and ordered to the generator.
later when coordinated with MEA and understood that the short circuit at connection points over 25%
.The solution is to change the generator, which TTCL ordered, by TTCL need to add up 35 million. This is the responsibility of the TTCL
.TTCL have purchased this generator, after NTP because it takes in the production 9 months Engineering 1 month sent another 2 months. But COD will be delayed 9 months or ask for meaParameter change in the system which connect several provinces, which mea't
final choice is the company to install equipment is Limiter. Reactor
equipment and Limiter meaNot because there is no software in an analysis on the level of current short circuit connection Imapact on Short Circuit Currents) and thus must stick Reactor.