Project study was aimed to investigate the production time of frozen food machine Out feed Table Assembly and find the causes of delay in the work. Study on starting process, laser cutting process of grinder deburring process fold.The process of cleaning up welding, assembling procedure. The steel cutting sawing machine, step, step milling turning operations study consists of design tool for data collection.How to save the time and distance, the flow of each stage. How to define standard work time each parts. Find the causes from the production process!The study results showed that The laser cut each piece average time is 5 minutes. The grinder to disparage each piece in 4 minutes. The folded folding time to fold 1 times to take 1 minutes.25 hours. The assembling process takes an average of 65.25 hours
.