Previously plan for June 8th but after boiler tuning done last Friday evening (June 3rd) so we agreed to commercial run the boiler by supplying steam to Dryer
right the way. De facto ,those equipment are in operation and handed over to you but I shall set a meeting to list out the pending work to be completed on project responsibility
and officially hand over to you. Sorry the inconvenience may cause regarding incompletion of the building/infrastructures which we will rush up.
Please aware of the boiler performance test shall set up soon and will impact to have Dryer uses only LPG for not more than 8 hrs approximately.
This will be informed to you separately.