Research results can be offered as to how to improve the work by reducing the amount of sessions to help improve technology in the process, you can use ready-made parts technology came all 3 update process is the Khan throat soil beams and pillars of the House in the Khan throat can process reduced from 14 days to 3 days to process the remaining beams, floor 1, down from 30 a day for 21 days and the rest of the process, down from a six-day House pole rest 3 days which can reduce cycle time, all from 151 days reduced to 127 days 15.89 percent and also have a cost analysis before you update all cost. 1,362,247.50 baht after update to 1,233,465.06 baht 9.45 percent, therefore, concluded that the construction process optimization technology to help make operations with better performance. This has resulted in a period of lower operation and lower cost make those reasons have increased profits. Also included, can meet the needs of our customers quickly.