-Rain water contamination at a new tank. Total quantity: 11.40 cubic meters, the new tank area and pond pumps and Remote area Impouding Basin, 1.83 and 0.79 8.78 quantity cubic meters, respectively, where the water tank in the rain area, patio and pond pump will flow through to Remote Impounding Basin by the rain water to flow into the oil extraction machine.(Oil Separator API) and rain water to extract the oil, and then will be delivered to the room collected wastewater ponds of 2 production line (Wastewater Tank Hold Up; TK809Zs) to a pond monitoring (Inspection Pit) before draining the rain through the criteria of hemaraj Eastern industrial estate (map Ta phut). Set into the water table of the hemaraj Eastern industrial estate (map Ta phut) and sent to a central waste water treatment system of the next nikhom.