- 1st payment of 20% when the contract
- 2nd installment payment of 20% when carrying out the needle pouring footings and beams, floor 1 completed
the implementation pouring columns 2 and place the finished surface layer, third layer 4 was completed.
- the third installment payment of 20% when performed only top post. 3, 4, and place the finished surface layer, third layer 4 finish
- fourth installment payment of 20% when performed only top post. 4, 5, and leave the finished surface layer 4 top 5 finish
when performing masonry finished 1st - 5th floor finish
- the period of the fifth pay 10% on the operating system, lights, frosted finish
- period. 6 pay 10% on the operating system, sanitary installations, tiles, sanitary ware and then painted and ready to deliver.