1. Ongoing deal - > GSB CCTV DS4700 replacement
Regarding the previouse storage was sized based on capacity only. But the system ifself contain heavy sequencial R/W workload (Approx 4.62Mbps / camera for recording). This generate lots of pain point regarding performance issues. Following activities is agreed to be done:
1.1 MTC/UCS , to gather existing storage utilization for both IIOP and Throughput to see what is the actual utilization for the current system.
1.2 UCS , to send following information regarding new storage design to match required performance/capacity.
Capacity and throughput requirement for each of storage pool
1) Production -> How many camera perform recording (Mbps???) and How many client running playback (mbps ???)
2) Archive storage pool -> How many times per day and how much data for each time??
1.3 UCS to send the solution diagram shown during the meeting solution and confirm the storage solution (NAS/SAN) the MileStone software support.
2. Future CCTV solution
In order to provide best solution we need to understand the solution as much as possible. Any documents regarding the solution overview and how the sizing was done would be preferred.