In quarter 2/2557 (2014) ST-5018 and GT-5017 a holiday company to connect the system's pipes, steam and water system, with the TOP 9 SPP project days and 12 days, respectively, and the annual maintenance plan, Major Inspection GT-5015 June 30 to August 4, 2014 for a period of 36 days.